Oct 11, 2010 #1 AAEC Civil/Environmental Joined Nov 22, 2006 Messages 42 Location US We have this void that extend below water table. What type of fill materials would you recommend? No major load will be acting over the fill.
We have this void that extend below water table. What type of fill materials would you recommend? No major load will be acting over the fill.
Oct 11, 2010 #2 oldestguy Geotechnical Joined Jun 6, 2006 Messages 5,183 Location US What ever you use, say its stone, sand, etc, keep the P-200 very low, certainly not over 5 percent. Upvote 0 Downvote
Oct 23, 2010 #3 adhmawy Civil/Environmental Joined Oct 23, 2010 Messages 1 For safety and non-settlement it is recommended to use either sand or at least sandy soil with minimum p200 Upvote 0 Downvote
For safety and non-settlement it is recommended to use either sand or at least sandy soil with minimum p200