Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Triangular Reinforcement Pattern for Strut and Tie Pyramid

Status
Not open for further replies.

canwesteng

Structural
May 12, 2014
1,704
I have a pile cap sitting on three piles, triangular to distribute loads evenly to the piles. My S&T model is basically a 3 sided pyramid. I'm going to lay the rebar out in a tringular pattern, but I'm wondering if there is any basis for laying the bar out in an orthogonal pattern, and then taking the capacity of the ties as the sine/cosine of the angle between the ties and the rebar. Any thoughts?
 
Replies continue below

Recommended for you

That would be acceptable, but I think the more traditional placement of bars in a triangular pattern, from pile to pile, is simpler.
 
I think triangular is much easier for analysis as well. I've just always defaulted to using either 2 larger piles or 4 smaller piles instead of 3, so I wasn't sure if triangular reinforcement is common.
 
Triangular has never been an issue when I have designed it that way. The only slightly tricky bit is to ensure the column is at the centroid of the 3 pile group.
 
I don't think getting the column in the centre is going to be hard, unless you mean during construction. I'm adding 2 inches of eccentricity in the S&T model to allow for them misplacing the piles.
 
I meant getting the piles in the right place. The column will be on a grid line, but the piles in one direction will be offset differently from a grid line so the centroid of the pile group coincides with the grid. Simple, I know, but sometimes set out wrong if not clearly shown on the drawings.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor