burnt2x
Electrical
- Oct 10, 2007
- 525
Hi,
I have a proposal to upgrade a distribution line 4 km long that is now loaded up. The load has increased from the design load of 600 kVA to around 1.3 MW (almost 2X) so that they opted to install gensets to the newer buildings.
Other than going into a higher transmission voltage (13.8), is there any other economical ways to meet a load of around 1.3 MW (do away with the gensets)?
Any comment would be helpful.
Respectfully,
burnt2x
I have a proposal to upgrade a distribution line 4 km long that is now loaded up. The load has increased from the design load of 600 kVA to around 1.3 MW (almost 2X) so that they opted to install gensets to the newer buildings.
Other than going into a higher transmission voltage (13.8), is there any other economical ways to meet a load of around 1.3 MW (do away with the gensets)?
Any comment would be helpful.
Respectfully,
burnt2x