tubsdua
Civil/Environmental
- Dec 18, 2011
- 27
We are executing a runway work for overlaying the turning pads of an operational runway. The overlay is unbonded type (white topping) i.e 75 mm DBM over existing rigid pavement and followed by 375 mm of 44 Kg/sq cm PQC.
Now the issue raised here is that after relaying the turning pad will be 450 mm higher than the flexible portion of runway and a ramp is to be provided with a gradient of 1:100 (as per ICAO). The ramp is to be laid up to 45m into the flexible portion to cater for 450mm of level difference.
Does anyone has any experience in a situation like this and how was the ramp provided? What is the post laying feedback and any lessons learnt or corrections reqd?
A few methodologies are attached as pdf files. The PQC is being layed with a fixed form paver. Points to be looked into:-
(a) The options with sloping PQC on flat ground is questionable (option 1 and
3).Maybe possible on sloping ground (option 2)?
(b) Laying of bituminous layers on PQC will have high possibility of
reflective cracking. Any comments/ideas on these aspect?
(c) Is excavating the existing flexible pavement recommendable (option 2 and 3)?
Suggestions and comments are welcome.
Best.
Now the issue raised here is that after relaying the turning pad will be 450 mm higher than the flexible portion of runway and a ramp is to be provided with a gradient of 1:100 (as per ICAO). The ramp is to be laid up to 45m into the flexible portion to cater for 450mm of level difference.
Does anyone has any experience in a situation like this and how was the ramp provided? What is the post laying feedback and any lessons learnt or corrections reqd?
A few methodologies are attached as pdf files. The PQC is being layed with a fixed form paver. Points to be looked into:-
(a) The options with sloping PQC on flat ground is questionable (option 1 and
3).Maybe possible on sloping ground (option 2)?
(b) Laying of bituminous layers on PQC will have high possibility of
reflective cracking. Any comments/ideas on these aspect?
(c) Is excavating the existing flexible pavement recommendable (option 2 and 3)?
Suggestions and comments are welcome.
Best.