I need to Know about the Factory Acceptance tests (FAT) for a 13.8KV/0.48 KV oil filled transformer.
The routine test include
1) Winding resistance
2) voltage ratio & check of voltage vector
3) measurement of impedance voltage & load losses
4) No load los & current
5) Dielectric tests
seperate source voltage withstand & induced overvoltage withstand test
6) Test for auxillary equipment & wiring
7) Test on OLTC
Which additional special test from below are also required
1) Temperature rise test
2) Dielectric test-Lightining impulse test
3) Dielectrica test-PD & Chopped wave LI
4) Measurement of zero sequence impedance on three phase transformer
5) Short circuit test
6)Measurement of acoustic sound level
7) measurement of harmonics on no load current
8) Leakage test for transformer tank.
the transformer is 900 KVA.
Thanks in advance
The routine test include
1) Winding resistance
2) voltage ratio & check of voltage vector
3) measurement of impedance voltage & load losses
4) No load los & current
5) Dielectric tests
seperate source voltage withstand & induced overvoltage withstand test
6) Test for auxillary equipment & wiring
7) Test on OLTC
Which additional special test from below are also required
1) Temperature rise test
2) Dielectric test-Lightining impulse test
3) Dielectrica test-PD & Chopped wave LI
4) Measurement of zero sequence impedance on three phase transformer
5) Short circuit test
6)Measurement of acoustic sound level
7) measurement of harmonics on no load current
8) Leakage test for transformer tank.
the transformer is 900 KVA.
Thanks in advance