TehMightyEngineer
Structural
Got a nice job that came across my desk for a bridge deck replacement. They want to utilize precast deck panels on the existing steel bridges with ultra-high performance concrete in closure pours between each panel. The panels are fairly complex pours but otherwise should be a great project.
The item I'm looking to get a second opinion on is the panels are heavily weighted on one end from a precast barrier and need to beleveled set to the proper elevation and load distriution using a number of leveling vertical adjustment screws. The specification requires that the panel load be evenly distributed by adjusting the torque on each leveling vertical adjustment screw to a torque schedule that we're to submit with our shop drawings. The tolerance for the final installed torque is to be +/- 15%.
Here's a picture of what these leveling screws will roughly look like:
The question I have is regarding the inherent difficulty in calculating bolt tension loads based on measured torques. I can obviously calculate the torque required to raise and lower eachleveling vertical adjustment screw up given a load on the bolt, but based on the RCSC recommendations these calculations have errors due to friction forces and bolt tolerances that exceed the tolerance in the specification for the contractor. This says nothing for the obvious real-world application of the bolts. Any dirt on the bolt or poorly lubricated threads will show a much higher torque which would result in the bolt being under or overloaded.
Is such a torque schedule feasible given the constraints? Is there a way to improve accuracy of calculating the torque that each bolt will need to evenly distribute the load?
I'm waiting to hear back from the engineer of record but figured I was going to make this post either way.
EDIT: Fixed terminology.
Professional and Structural Engineer (ME, NH)
American Concrete Industries
www.americanconcrete.com
The item I'm looking to get a second opinion on is the panels are heavily weighted on one end from a precast barrier and need to be
Here's a picture of what these leveling screws will roughly look like:
The question I have is regarding the inherent difficulty in calculating bolt tension loads based on measured torques. I can obviously calculate the torque required to raise and lower each
Is such a torque schedule feasible given the constraints? Is there a way to improve accuracy of calculating the torque that each bolt will need to evenly distribute the load?
I'm waiting to hear back from the engineer of record but figured I was going to make this post either way.
EDIT: Fixed terminology.
Professional and Structural Engineer (ME, NH)
American Concrete Industries
www.americanconcrete.com