mccheynebeeman
Electrical
- Feb 28, 2006
- 30
Hi there,
It seems to me like finding the answer to the question above is a black art on its own, but I'll throw it out there in hopes that someone can give me a more definite answer.
The basement I plan on building will be formed using IFC block (3" Styrofoam/side 6" gap for concrete) at a height of 10ft. The dimensions are 46' X 26' roughly and the house to be moved on is a bungalow. I understand that concrete needs approx 22-26 days to fully cure, however my dad (civil engineer) suggested that my house could be moved on merely 3 days after the pour (this does not include backfilling). Is 3 days enough time?
Another question I have is that I have been assured that the 6" of concrete within the IFC is up to code for a 10ft high foundation wall, however all my findings seem state that 8" - 10" thick walls are required for that height. The basement will only be backfilled 6ft.
Thank you for your time,
Frazer RM Ross
It seems to me like finding the answer to the question above is a black art on its own, but I'll throw it out there in hopes that someone can give me a more definite answer.
The basement I plan on building will be formed using IFC block (3" Styrofoam/side 6" gap for concrete) at a height of 10ft. The dimensions are 46' X 26' roughly and the house to be moved on is a bungalow. I understand that concrete needs approx 22-26 days to fully cure, however my dad (civil engineer) suggested that my house could be moved on merely 3 days after the pour (this does not include backfilling). Is 3 days enough time?
Another question I have is that I have been assured that the 6" of concrete within the IFC is up to code for a 10ft high foundation wall, however all my findings seem state that 8" - 10" thick walls are required for that height. The basement will only be backfilled 6ft.
Thank you for your time,
Frazer RM Ross