Hi Guys:
I have come to the conclusion when it comes to detailing something to be done just so, that it seldom happens. More often than not, well meaning and "lazy" workmen just do it the easy way. Instead of carefully placing 12 inches next to a wall, a whole bucket load from an end loader is dumped in and maybe spread a little, but more likely not. Ask for 12 inch layers and they vary from 6 to 20 inches, or more.
Thus, it is easier and about the same cost to spec. the whole backfll to be granular fill, to be sure you get what you want.
So, the simpler you can make it, the more likely it is done right where you need it.
These things are stated since these days it seldom possible to be aware of everything on a job, especially non critical work.