CWIGGPE
Mechanical
- Dec 29, 2014
- 2
I have been asked to provide an engineering certification of an existing (already in-place) temporary concrete batch plant. The plant will be in place for 6 months. It is located in a hurricane-prone region and also a Seismic Design Category D. Given the height and weight of the structure, both wind and seismic are major factors. The weight of the plant helps me with wind stability, but the seismic forces are a problem. Batch plants have large silos 60' tall and the overturning at the base is large. The company I am working with uses these plants all over the U.S., and not once have they been required to anchor them or provide engineering given their temporary nature, until now.
My questions are -
Do you think ASCE 37-14 applies to this situation? I can rationalize it this way - the plant is technically a construction-related entity used to facilitate the construction of a major road. However, while it is a temporary structure itself, I don't feel it is temporary in the way that ASCE37 states mean it to be temporary, as in bracing or shoring. Of course, ASCE37 would exempt the plant from seismic design altogether given S1 is less than 0.40, assuming the local building authority allows it. If not exempt, it could at least be reduce substantially per 6.5.2.
If ASCE37 cannot be applied, are there any other options for decreasing the seismic loading to avoid massive footings and anchorage? I tend to lean towards requiring them to meet all the provisions of ASCE7, but that will mean shutdown, massive expenditure, and huge waste for a statistically unlikely seismic event.
Thanks for your help
Cwigg951
My questions are -
Do you think ASCE 37-14 applies to this situation? I can rationalize it this way - the plant is technically a construction-related entity used to facilitate the construction of a major road. However, while it is a temporary structure itself, I don't feel it is temporary in the way that ASCE37 states mean it to be temporary, as in bracing or shoring. Of course, ASCE37 would exempt the plant from seismic design altogether given S1 is less than 0.40, assuming the local building authority allows it. If not exempt, it could at least be reduce substantially per 6.5.2.
If ASCE37 cannot be applied, are there any other options for decreasing the seismic loading to avoid massive footings and anchorage? I tend to lean towards requiring them to meet all the provisions of ASCE7, but that will mean shutdown, massive expenditure, and huge waste for a statistically unlikely seismic event.
Thanks for your help
Cwigg951