We are running temporary power and control cables to a piece of equipment. It has been proposed to run the cables on the ground for a couple weeks while permanent structural supports are constructed to route the raceway overhead. I looked i nthe code and wasn't able to find anything prohibiting the cables being installed on the ground. I have a safety guy who disagrees and says all temporary cable was be supported off the ground.
This may come down to the AHJ, but wanted to get some feedback from you guys who have possibly run exposed cable (suitable for wet environment) directly on the ground for a temporary basis and had approval from an inspector.
Thanks in advance.
This may come down to the AHJ, but wanted to get some feedback from you guys who have possibly run exposed cable (suitable for wet environment) directly on the ground for a temporary basis and had approval from an inspector.