piledrvr
Civil/Environmental
- Feb 1, 2005
- 5
I am looking for ideas on how to tie-back a temporary shoring wall. Our current plan is to cast some rather large deadmen and use coilrod to tie back the pile. The problem with this approach is that the deadmen would be located within a embankment area and will interfere with the placement of the fill. I have looked at the Manta-Ray system, but everything I have seen says that it can only be used in "undisturbed" soils. We have also thought about driving a couple of anchor pile after the fill has been placed and cut these off below grade, but then we lose the piling. Any other ideas?