Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations TugboatEng on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Tasks not assigned

Status
Not open for further replies.

stjuste101

Computer
Joined
Sep 25, 2007
Messages
28
Is there a view where you can see all the tasks not assigned? I'm not referring to the gantt chart view. I'm referring to a view where you only see the tasks that haven't been assigned. Something that shows the project name and tasks not assigned yet.
 
Are you talking about MS project?

This is a general project management forum so you'll need to clarify.

I'm not sure if there is a specific project forum under
KENAT, probably the least qualified checker you'll ever meet...
 
The OP knows where it is, since he's posted there before.

Have you looked at the Resource Usage View? The first set of items are the unassigned tasks.

TTFN

FAQ731-376
 
Sorry for putting my post on this forum.

I know where the microsoft project forum is.

Thanks,
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top