When in task information (Pj2000) one can see the task duration field everywhere. But no way to see the task work field... where from can it be accessed ?
This is very important for me for i'm looking for a way to schedule task (operating returned mail) which I know will last for 2 weeks and use up to say 30 hours secretary hours... and i believe the most accurate way to let project calculate things is simply to enter things properly, avoiding :
- end and start date for the task shan't be use for that purpose (and are unknown as yet since beginning is not scheduled).
- contouring seems to be related to the assignment of each sources, when what i want is to get a : N hours needed per day on that period, just to schedule the secretaries on that task for each day.
I start to wonder if that field actually exist (crazy isn't it ?) when the help file states at different places that this field exist
Thanks to help,
-------------
The help file states at different places that this field exist :
"Work is different from task duration. For example, a resource may require 32 hours of work to complete a task, but the task may be scheduled with a duration of 2 days. This indicates that more than one resource needs to be assigned to this task, namely two. Working 8 hours a day on the task, two people would complete the task in 2 days."
G.P.L. ZINS
Field operations director in Marketing research Paris France
This is very important for me for i'm looking for a way to schedule task (operating returned mail) which I know will last for 2 weeks and use up to say 30 hours secretary hours... and i believe the most accurate way to let project calculate things is simply to enter things properly, avoiding :
- end and start date for the task shan't be use for that purpose (and are unknown as yet since beginning is not scheduled).
- contouring seems to be related to the assignment of each sources, when what i want is to get a : N hours needed per day on that period, just to schedule the secretaries on that task for each day.
I start to wonder if that field actually exist (crazy isn't it ?) when the help file states at different places that this field exist
Thanks to help,
-------------
The help file states at different places that this field exist :
"Work is different from task duration. For example, a resource may require 32 hours of work to complete a task, but the task may be scheduled with a duration of 2 days. This indicates that more than one resource needs to be assigned to this task, namely two. Working 8 hours a day on the task, two people would complete the task in 2 days."
G.P.L. ZINS
Field operations director in Marketing research Paris France