MichaelBerrier
Computer
- Oct 30, 2005
- 1
I've got a series of tasks that all need to occur on the same day. The duration of the tasks is measured in hours. The start of one task is dependent on the completion of the other. When I enter a predecessor for the next task, it tries to force me to use the next day instead of the task occuring on the same day. I'm sure there is a way to do this but didn't find it in my MS Project book.
Michael
Michael