We have a 60 MW hydro-generator to be put into operation soon. I work on the design side and have a tests program for the generator. It is required that the generator can also operate in a synchronous compensation mode. I know the procedure. The water is removed from the turbine and the machine will operate in synchronous mode.
I am being asked to prepare a schedule of tests for synchronous compensation, but I do not know what tests are necessary. I do not know a standard (IEC, CEI, NEMA...) where these tests are specified. If anyone knows this problem please let me know. Thank you in advance.
I am being asked to prepare a schedule of tests for synchronous compensation, but I do not know what tests are necessary. I do not know a standard (IEC, CEI, NEMA...) where these tests are specified. If anyone knows this problem please let me know. Thank you in advance.