i agree to EDZ.., RUS.
BAker tester is also comparable to the test set up or procedure using ELECTROVOM surge comparison tester.
it is only that there is a 4 test probes that is 1, 2, 3 probes are for the so called hot leads, and fourth is the ground lead (for the frame).
simply, hooked up the hot leads (1,2,3) to the motor leads (wye or delta - T1,T2,T3 or U,V,W)in any order provided it's a three leads out (otherwise you configured your connection to obtain three leads out), then proceed to the test equipment's toggle switches and test voltage knobs to test the motor winding.
you might noticed in testing on wye connectecd motor the waveform reflected on the screen is more than as compared to delta connected.since wye connected coils have more resistance as compared to delta.
in the case on using two leads at a time, its also allowable as what EDS cited..
but in testing on the group of coils as in partially rewinded pre-formed coils or it was just formed, you must configure the coil leads to fit to the test leads of the surge tester that is you will combine test leads 3 and ground lead, and 1, 2 leads will then be your hot leads to test the coils or group of coils.