Dear all
In order to make a tie-in to the exising subsea pipeline, it seems for me the best way is to employ the hot-tapping in case the system shutdowm is not permitted. But if it is permitted for a certain period, does anyone has any idea what method should be applied in term of engineering, cost effectiveness and also for future matainence accessibility. Your help will be very appreciated.
Thank You Very Much
In order to make a tie-in to the exising subsea pipeline, it seems for me the best way is to employ the hot-tapping in case the system shutdowm is not permitted. But if it is permitted for a certain period, does anyone has any idea what method should be applied in term of engineering, cost effectiveness and also for future matainence accessibility. Your help will be very appreciated.
Thank You Very Much