StevenHPerry
Mechanical
- Sep 15, 2006
- 210
For stub ups from underground piping, what accuracy (and/or precision) do you design for? What is actually achieved by construction?
Of course there's a story behind this. On a recent job, a nameless construction partner was off from a namless design firm's coordinates by more than a foot and of course only 3" of clearance was designed. I've witnessed essentially the same problem at multiple design firms and multiple constrution firms. It seems to be accepted as a fact of life. Anyone have a different experience?
- Steve Perry
This post is designed to provide accurate and authoritative information in regard to the subject matter covered. It is offered with the understanding that the author is not engaged in rendering engineering or other professional service. If you need help, get help, and PAY FOR IT.
Of course there's a story behind this. On a recent job, a nameless construction partner was off from a namless design firm's coordinates by more than a foot and of course only 3" of clearance was designed. I've witnessed essentially the same problem at multiple design firms and multiple constrution firms. It seems to be accepted as a fact of life. Anyone have a different experience?
- Steve Perry