Hi all,
I want to know how to connect slab to retaining wall at each floor levels in under ground structure.Do i have to draw a beam at each floor level on retaining wall and slab junction to transfer loads.
 
You devide the wall to meet slab gap. No need to draw boundary beams.
 
If the nodes do not coincide, I think you should you the Edit Points > connect method.
 