Jul 10, 2010 #1 MEEZ Civil/Environmental Joined Jun 9, 2010 Messages 2 Location US I am modeling this long/deep stormdrain system and I have majority of the system flowing full. Although I am meeting the HGL requirements, I wonder if I need to upsize the pipes, since its based open channel/backwater analysis?
I am modeling this long/deep stormdrain system and I have majority of the system flowing full. Although I am meeting the HGL requirements, I wonder if I need to upsize the pipes, since its based open channel/backwater analysis?
Jul 10, 2010 #2 cvg Civil/Environmental Joined Dec 16, 1999 Messages 6,868 Location US stormcad analyzes using pressure flow, not just open channel Upvote 0 Downvote
Jul 10, 2010 Thread starter #3 MEEZ Civil/Environmental Joined Jun 9, 2010 Messages 2 Location US Thanks, Upvote 0 Downvote