kashain
Mechanical
- Mar 2, 2011
- 11
My elevator contractor uses the steel deck to support the transformer and elevator controller and claims that the support will be embedded in the concrete when the concrete is poured.
How should I tell the contractor they are wrong and they have to remove the equipment and support the equipment to the finished concrete later.
How should I tell the contractor they are wrong and they have to remove the equipment and support the equipment to the finished concrete later.