Hello everybody:
The engine was started up.
Check outs before starting: stop tests (trip tests) of Oil Mist Detector, low lube oil pressure, local and remote emergency stop.
- Cold deflexion of crankshaft.
- The Oil Mist Detector was checked, specially serviced and adjusted to its lower value.
- Starting and stoping the pre lube oil pump for lube oil circulation through all bearings, crankshaft, etc. and to see where this lube oil comes from and goes to.
- Pre heat the engine with the High Temperature water system.
- With the lube oil pump on, pre heater pump on and fuel oil on, rotate the engine with the turning gear during 15 minutes.
- Rotate the engine with starting air blow for around 30 seconds.
Starting up.
- The engine is started up and run idle during 1 minute, then is stopped with the Oil Mist Detector.
Once the engine has stopped, we proceed to open the crank case covers and check the temperature of all the bearings: main bearings, big end and small end bearings. For this activity we use an infrared meter and a thermal camera.
We verify the free axial movement (along the connecting rod journal) of the big end connecting rod.
- Everything was OK. Start and run idle during 5 minutes, then stop with the low lube oil pressure trip setting.
At this moment, we achieve the same controls stated above.
Besides that check outs, we check for leaks of: fuel oil, lube oil, water and starting air.
- Everything is OK. Start and synchronize the unit taking 1.000 kW load and run during 3 minutes. Stop the unit with low lube oil pressure trip setting.
Here we check one more time the temperatures and the free movement of the con rods.
- Everything is OK. Start and synchronize, then run with 3.000 kW during 5 minutes. Stop with the local emergency shutdown.
Check out once again.
- Start and synchronize, then run during 30 minutes with a load of 5.000 kW, then with 6.800 kW, 10.200 kW, 11.900 kW, 13.600 kW, 15.300 kW and finally, with 17.000 kW.
After the 30 minutes with each level of load, the engine was stopped and left run idle for 5 minutes after which, the check outs of temperatures and movement were achieved.
- After the unit ran at the nominal capacity, Hot deflexions of crankshaft were taken.
- After 10 hours of operation at full load, the main bearings A8 and B8 were checked out and the big end bearings A8 and B8 were replaced for new ones.
The crank case covers A8 and B8 were painted in yellow and red in order to warn that a special condition on that side has ocurred. An inscription was properly painted on these covers indicating the modifications and showing the part numbers of the new elements.