clooney
Mechanical
- Jan 12, 2005
- 17
Hi guys,
here is the situation:
The process plant construction is completed. All equipments, pipes and relevent supports and Springs are in place. PLANT NOT IN OPERATION YET. At this stage, supports are basically bearing the Dead Load of the piping system.
The inspector arrives at the site and wants to verify the compressor nozzle alignment with connected piping before he OK's it for start up. Upon unbolting the pipe flange from compressor nozzle, the pipe flange disengages from the nozzle and pipe moves upward by 60mm about 2.4" (by the way, the horizontal misalignment was insignificant). The inspector does not approve of this large of a gap between the pipe flange and the compressor nozzle.
Noteworthy:
i) The nozzle is oriented vertically upward.
ii) The vertical pipe run (40" n.p.s.)connected to the nozzle is approx. 3 meters (10') long and is supported by Double Can Spring Supports.
iii) The Horizontal run immediately after the vertical run is also supported by a single spring hanger.
iv) The contractor has removed the lock pins from these springs (i.e.; the springs were not locked during this inspection).
My questions:
1)Should the springs be locked during this inspection at the preset cold load? Or is it O.K. to remove the lock pins.
2) Is this 2.4" vertical gap pretty significant?
3) How far would you go (percentage-wise)with field adjusting the spring supports if the design cold loads differ from the actual (as-built)cold loads. Note that the springs were delivered locked at the preset cold loads specified by the designer.
Thanking you in advance,
C
here is the situation:
The process plant construction is completed. All equipments, pipes and relevent supports and Springs are in place. PLANT NOT IN OPERATION YET. At this stage, supports are basically bearing the Dead Load of the piping system.
The inspector arrives at the site and wants to verify the compressor nozzle alignment with connected piping before he OK's it for start up. Upon unbolting the pipe flange from compressor nozzle, the pipe flange disengages from the nozzle and pipe moves upward by 60mm about 2.4" (by the way, the horizontal misalignment was insignificant). The inspector does not approve of this large of a gap between the pipe flange and the compressor nozzle.
Noteworthy:
i) The nozzle is oriented vertically upward.
ii) The vertical pipe run (40" n.p.s.)connected to the nozzle is approx. 3 meters (10') long and is supported by Double Can Spring Supports.
iii) The Horizontal run immediately after the vertical run is also supported by a single spring hanger.
iv) The contractor has removed the lock pins from these springs (i.e.; the springs were not locked during this inspection).
My questions:
1)Should the springs be locked during this inspection at the preset cold load? Or is it O.K. to remove the lock pins.
2) Is this 2.4" vertical gap pretty significant?
3) How far would you go (percentage-wise)with field adjusting the spring supports if the design cold loads differ from the actual (as-built)cold loads. Note that the springs were delivered locked at the preset cold loads specified by the designer.
Thanking you in advance,
C