CMcF
Mechanical
- May 28, 2003
- 149
I am designing an assembly station in which a splined hub and shaft are assembled. "99 times out of 100"", the shaft will just slide into the hole under its own weight. But some times it will need a bit of help. Call me cynical but I was not surprised to learn that nobody could quantify a maximum insertion load before the assembly should be rejected. But I have to design the machine anyway. It would be nice if I could justify using a medium sized pneumatic cylinder, instead of a hydraulic ram. Your comments and help will be much apreciated.