L775
Structural
- Feb 4, 2001
- 48
Hi,
This question is related to case is Dade County, Florida.
A spill of contaminant from a dry cleaner is being monitored with minitoring wells for the last 2 to 2.5 years. the DERM is expected to issue what is called an MOP (Monitoring Only Plan)and after that a NFA (No Further Action).
1. would anyone be able to approximate and explaine the various steps and their complexities all the way up to NFA.
2. would an NFA be sufficient and final in terms of future inquiries related to the case?
What is the importance of the above in terms of considering buying the subject property knowing that an MOP will be issued before closing and an NFA to follow after closing on the property purchase transaction?
Thanks,
This question is related to case is Dade County, Florida.
A spill of contaminant from a dry cleaner is being monitored with minitoring wells for the last 2 to 2.5 years. the DERM is expected to issue what is called an MOP (Monitoring Only Plan)and after that a NFA (No Further Action).
1. would anyone be able to approximate and explaine the various steps and their complexities all the way up to NFA.
2. would an NFA be sufficient and final in terms of future inquiries related to the case?
What is the importance of the above in terms of considering buying the subject property knowing that an MOP will be issued before closing and an NFA to follow after closing on the property purchase transaction?
Thanks,