Thank you for your response. To be honest, when I look at the literature, there doesn’t seem to be a universally agreed-upon number of traverses. However, it is generally recommended to perform at least two measurements. Previously, four measurements were conducted at the turbine site, and initially, I also stated that four measurements would be sufficient. However, due to the increased cost, I reduced it to two measurements. The client is now skeptical about whether two measurements would be adequate. The lack of a clear standard for the number of measurements is frustrating. While increasing the number of measurements provides more data, it also raises the cost for the client. Unfortunately, I don’t have a definitive source to substantiate the recommended number of traverses.