ASCE 7 says to use 20% of any snow load greater than 30psf as seismic weight. This causes a problem for the 0.6D+0.7E load combination. The snow load acts as seismic weight, but does not resist uplift and overturning. Can't the 20% be used to resist uplift and overturning if it's included as seismic weight?