As a CWI you should know to refer to the WPS and the applicable welding standards to answer your own question.
It is very disappointing to have a CWI ask such a basic question. Regardless of which open code book examination you took, you should have learned that it is your responsibility as a CWI to refer to the applicable documents to determine if there are limitations on such things as the width of individual weld beads or layers, heat input, interpass temperature, etc.
As a third party CWI, your job is to verify the welders are working within the parameters of the approved WPSs. In other words, you need a copy of the applicable WPSs, codes, and contract documents to see what is required and what is approved. You don't make the rules, you only verify they are followed.
If you are working as QC for your employer; a manufacturer or contractor, you may have the responsibility of verifying the welders are adhering to the parameters of the WPS, however, in accordance with AWS B5.1 Table 1, it is not within the scope of a CWI's responsibility to develop WPSs. Still, you need to refer to the applicable contract documents to determine if there are limitations that need to be addressed.
If, after researching the applicable documents, you still have concerns, you should be directing them to the appropriate individuals in your organization or the EOR.
You didn't mention what code or welding standard is being invoked by the contract. That is the first question that must be answered. Next, what base metals (material specifications) are being welded? After that, what is the application or service environment? Only after those questions are answered can a meaningful response be provided. Answers to those questions should also be answered by a close review of the contract documents.
Best regards - Al