There is a small area (about 50 square feet of an existing slab on grade that is only 2" thick and is underlain by sand base which seems reasonably well compacted. The slab on grade in the remaining area of the building (which was built in 1966) is 6" thick. I believe the 2" thick slab was placed about 25 years ago, probably unknown to the architect at the time, when underground ducts were re-routed when an addition was built onto the building. The room in which this 50 square feet of 2" slab occurs is used as an accounting office, the office is about 20 feet square and had vinyl tile on it. It has performed satisfactorily to-date. A recent flood required removal of the vinyl tile, and when I chain dragged the concrete surface I identified this area of thinner slab by the very hollow sound when the chain passes over it (as well as by the change in appearance from the adjacent slab). However when we drilled an exploratory core hole, we did not find any signifcant void under the slab, but we did find that the slab was only 2" thick.
Questions:
1) To-date there has been only a desk on the 2" slab area, but the owner wants to have the flexibility to place filing cabinets anywhere in this room. Should we take out the 2" slab at this time, or do you think that a 2" slab is sufficient to support filing cabinets? I have no confidence that the Westergaard equations work in this case.
The cost of replacing it with a 6" slab matching the remainder of the slab in the building, including some dowels, is $3000.
I figure that the filing cabinets contents probably would not exceed about 20 pounds per foot. So 4 drawers, each 24" deep would be about 160 pounds plus the weight of the cabinet would be about say another 100 pounds = 260 pounds. Does not seem like that much weight.
2) Are there other reasons to replace the 2" slab. I have never heard of a 2" slab on grade.
Questions:
1) To-date there has been only a desk on the 2" slab area, but the owner wants to have the flexibility to place filing cabinets anywhere in this room. Should we take out the 2" slab at this time, or do you think that a 2" slab is sufficient to support filing cabinets? I have no confidence that the Westergaard equations work in this case.
The cost of replacing it with a 6" slab matching the remainder of the slab in the building, including some dowels, is $3000.
I figure that the filing cabinets contents probably would not exceed about 20 pounds per foot. So 4 drawers, each 24" deep would be about 160 pounds plus the weight of the cabinet would be about say another 100 pounds = 260 pounds. Does not seem like that much weight.
2) Are there other reasons to replace the 2" slab. I have never heard of a 2" slab on grade.