I'm assuming those are helical piles. It is not uncommon for them to be 4" or so off centerline. I've come to the conclusion you need a portion of the slab to resist the torsion from this eccentricity. Forget about the grade, many times the foundation is basement, well below grade.
I'd thicken the slab and connect it to the grade beam and reinforce the connection and slab accordingly.