a10jp
Electrical
- May 18, 2005
- 150
I am not a structural engineer, but I wish to consult with others if what I have here is a problem.
What I am showing (attached) is a slab in grade pad with a concrete precast u-trench section on top, and the pad is about 347" x 120". The actually rebar dimensions are D16, at 150mm (or 6”) spacing, top to bottom. The way our contractor do this is first pour the bottom part, where I indicated it in red line. Let it cured, then place the precast, and pour the rest. There is actually rebar connection between the top and bottom pour, it just that it is 2 different pours, and some people were extremely concerned now we have a split pad at the horizontal plane, and it is “cold joint”. They claimed there will be a problem if we have an earthquake. And because of that, they want one monolithic pour, instead of 2 separate pours. But my reasoning is, they are joined by the D16 rebars, it would be just like placing a concrete pad on a mud slab, where is there such a big different for a slab in grade. Also, just to clarify, the top slab is elevated above grade by 2”, the rest will be backfilled.
I am not structural engineer, but I just want to understand if there is truly a big issue here. ALso the equipment that will be placed on this is about 50,000lbs.
What I am showing (attached) is a slab in grade pad with a concrete precast u-trench section on top, and the pad is about 347" x 120". The actually rebar dimensions are D16, at 150mm (or 6”) spacing, top to bottom. The way our contractor do this is first pour the bottom part, where I indicated it in red line. Let it cured, then place the precast, and pour the rest. There is actually rebar connection between the top and bottom pour, it just that it is 2 different pours, and some people were extremely concerned now we have a split pad at the horizontal plane, and it is “cold joint”. They claimed there will be a problem if we have an earthquake. And because of that, they want one monolithic pour, instead of 2 separate pours. But my reasoning is, they are joined by the D16 rebars, it would be just like placing a concrete pad on a mud slab, where is there such a big different for a slab in grade. Also, just to clarify, the top slab is elevated above grade by 2”, the rest will be backfilled.
I am not structural engineer, but I just want to understand if there is truly a big issue here. ALso the equipment that will be placed on this is about 50,000lbs.