HamidEle
Electrical
- Feb 20, 2007
- 309
We are doing a commisioning test for a motor(No load). we need to rent a genset to start VFD Motor. This motor is a constant torque motor. VFD and Motor is 2MW. Do we need to rent a genset larger than 2MW in order to start the motor, even for VFD application?
Thanks in advance.