rittz
Structural
- Dec 30, 2007
- 200
A contractor built a garage attached to the house. He poured 12" piles 8 ft deep under an 8" x 24" grade beam for a foundation. The grade beam was lightly dowelled to the existing foundation. There was a 2 ft deep trench around the perimeter (excavation not yet backfilled) the trench filled up with water during a heavy rain, softened the clay soil around the piles (naturally lost the skin friction) and the piles subsided 2 or 3 inches. Obviously 8 ft friction piles are inadequate for starters. The garage wall and the roof pulled away 1 or 2 inches from the house. I have thought of a couple ways to underpin the grade beam. Anyone gone through anything similar? A void form is required under the grade beam to avoid grade beam heaving in highly plastic clay.