CavemanJones
Mechanical
- Mar 21, 2010
- 21
Hello guys,
My company uses V guides on short conveyors and they have been bending a v guide plate and bending vendors seem to have trouble getting them perfectly flat. So we would use a jack screw from bottom on a bar to level it off.
We are trying to eliminate the extra support and screw and go to 2 plates that are bent in some form to allow v guide to go between. I was examining it and trying to determine if I need to support plate or if I can dial in a thickness that will only require bolting from the channel.
I was using a simple beam calc and cantilevering from one side, accounting for half the uniform load. I come up with a plate around 7 GA min. This would be worse case, however I know with the plate on the other side it will support this application tremendously. I can't seem to find a equation for this. I am currently going thru school and I haven't learned how to build formulas like this equation. Can anyone here provide me any help on this application?
See attachment, I am taking worse case with uniform load and conveyor length 24" (the z to the sketch)
Thanks
My company uses V guides on short conveyors and they have been bending a v guide plate and bending vendors seem to have trouble getting them perfectly flat. So we would use a jack screw from bottom on a bar to level it off.
We are trying to eliminate the extra support and screw and go to 2 plates that are bent in some form to allow v guide to go between. I was examining it and trying to determine if I need to support plate or if I can dial in a thickness that will only require bolting from the channel.
I was using a simple beam calc and cantilevering from one side, accounting for half the uniform load. I come up with a plate around 7 GA min. This would be worse case, however I know with the plate on the other side it will support this application tremendously. I can't seem to find a equation for this. I am currently going thru school and I haven't learned how to build formulas like this equation. Can anyone here provide me any help on this application?
See attachment, I am taking worse case with uniform load and conveyor length 24" (the z to the sketch)
Thanks