Shuttle Conveyor

Status
Not open for further replies.

KDiz

Mechanical
Joined
Feb 25, 2008
Messages
7
Location
CA
Currently have a shuttle conveyor and chute to load concentrate into rail cars. The chute dumps the concentrate into the middle of the cars, creating a peak down the middle. Obviously this needs to be sorted out. Anyone have a good resource for this type of re-design or any helpful suggestions???
Thanks!
 
Get shorter rail cars.
 
Move/position the cars to spread the dumping point
Move/position the chute to spread the dumping point
Fit a two-way (or oscillating) deflector at the end of the chute
Fit a mechanical spreader at the end of the chute
Vibrate the cars to level the load
Employ manual labourers to spread the load
 
Hi KEnglish,

for an example, check and similar
(disclaimer: I'm in no link with this company).
Loading railcars is, in my exp., today a 'hightech' undertaking, as schedules are tight and overall tech specs have got to high levels. Also, railways tend to be tough with demands towards treating their equipment.
Regards

Roland
 