Show only workong hours in Ghant chart

Status
Not open for further replies.

segmentation

Bioengineer
Joined
Feb 27, 2008
Messages
3
Location
UA
I wish to make a week planning
Thus I wish that I have 5 days on my screen in Ghant chart
But MS project shows the whole day timeframe (0:00 - 24:00), which is not convinient.
How can I make it show only working hours?
 
The Gantt chart doesn't have the ability to show only 5 working days. The only view I know that can show just 5 days is the calendar view. You can always adjust the time the timescale on the Gantt charts to show varying densities of time.

Good luck
E Lehnert, PMP, Microsoft Certified Trainer - MS Project
 
The Gantt chart doesn't have the ability to show only 5 working days. The only view I know that can show just 5 days is the calendar view. You can always adjust the time the timescale on the Gantt charts to show varying densities of time.

Good luck
E Lehnert, PMP, Microsoft Certified Trainer - MS Project
 