KootK
Structural
- Oct 16, 2001
- 18,589
The Canadian concrete manual has a supplement where they discuss (very briefly) the mechanisms that can be used to resist shear delivered to a pile cap assemblage. I've encountered this in the context of working on a shear wall foundation system.
Anyhow, they suggest four possible mechanisms:
1) Friction between the pile cap and soil below.
2) Passive bearing of the pile cap / shear key against the adjacent soil.
3) Passive bearing of the piles themselves against the soil.
4) Bearing of the pile cap / shear walls against the adjacent slab on grade (where available).
After listing these mechanisms, they also state that "all four mechanisms may not act concurrently". So my question is this: Which do act concurrently and in which order do they engage? I'd appreciate any insights that others may have. Additionally, does anyone know of any good references that deal with this topic?
Some of my thoughts on the issue are:
a) My guess as to the order of mechanism engagement would be as follows: 1) Friction 2) Friction gives and SOG bearing takes over 3) SOG bearing gives and passive soil bearing (piles and pile cap concurrently) takes over. Following this logic, the piles and pile cap bearing against the soil would be the only mechanisms to act concurrently. Sound reasonable?
b) If you decide to use passive bearing of the pile cap against the soil, is it wise to use a lean concrete backfill between the pile cap and the extents of the excavation to ensure proper bearing against undisturbed soil?
c) Is it really appropriate to use friction between the pile cap and the soil? With piles absorbing the bulk of the gravity load via end bearing, wouldn't the amount of friction developed between the pile cap and the soil be quite limited (and difficult to predict). My thinking is that the soil under the pile cap would tend to settle away from the underside of the cap over time. Thoughts?
Anyhow, they suggest four possible mechanisms:
1) Friction between the pile cap and soil below.
2) Passive bearing of the pile cap / shear key against the adjacent soil.
3) Passive bearing of the piles themselves against the soil.
4) Bearing of the pile cap / shear walls against the adjacent slab on grade (where available).
After listing these mechanisms, they also state that "all four mechanisms may not act concurrently". So my question is this: Which do act concurrently and in which order do they engage? I'd appreciate any insights that others may have. Additionally, does anyone know of any good references that deal with this topic?
Some of my thoughts on the issue are:
a) My guess as to the order of mechanism engagement would be as follows: 1) Friction 2) Friction gives and SOG bearing takes over 3) SOG bearing gives and passive soil bearing (piles and pile cap concurrently) takes over. Following this logic, the piles and pile cap bearing against the soil would be the only mechanisms to act concurrently. Sound reasonable?
b) If you decide to use passive bearing of the pile cap against the soil, is it wise to use a lean concrete backfill between the pile cap and the extents of the excavation to ensure proper bearing against undisturbed soil?
c) Is it really appropriate to use friction between the pile cap and the soil? With piles absorbing the bulk of the gravity load via end bearing, wouldn't the amount of friction developed between the pile cap and the soil be quite limited (and difficult to predict). My thinking is that the soil under the pile cap would tend to settle away from the underside of the cap over time. Thoughts?