npthao121
Structural
- May 19, 2003
- 42
Dear all,
I’d like to know your advices in the following case:
Soil profile:
1st layer: Sandy clay (CL-ML), 2.2m thick. SPT = 8
Wn=21.2, Wl=22.0, Wp=16.4, Ip=5.6. Void ratio e = 0.853, saturated degree S = 66%
DSS test gives: phi=24o, C=0.099 kg/cm2.
Sieve analysis gives: gravel (7%), sand (75%), silt (9%), clay (11%)
2nd layer: Organic silts (OL), 3.0m thick. SPT = 5
Wn=33, Wl=41.2, Wp=22.3, Ip=18.9. Void ratio e = 1.07, S = 93%
DSS test gives: phi=10, C=0.143 kg/cm2
Sieve analysis gives: gravel (1%), sand (32%), silt (25%), clay (42%)
3rd layer: Sandy clay (CL-ML), thickness varies from 3.0 – 8.5m. SPT = 9
Wn=20.4, Wl=21.8, Wp=15.8, Ip=6.0. Void ratio e = 0.71, S=76%
DSS test gives: phi=24, C=0.098
Sieve analysis gives: gravel (9%), sand (74%), silts (6%), clay (11%).
4th layer: Organic silts (OL), thickness varies from 2.5 – 6m. SPT = 7
Wn=22.9, Wl=28.2, Wp=16.8, Ip=11.4. Void ratio e = 0.724, S=85%
DSS test gives: phi=15, C=0.166
Sieve analysis gives: gravel (3%), sand (52%), silts (21%), clay (24%)
End of boring log.
Question: Could shallow foundation be applied for this case? The contact pressure at bottom of footing is approximately 10 ton/m2 (this is the two stories building). What potential problem may occur?
Shear strength parameters are not so bad; but, consolidation settlement of the foundation seems to be occur (however, consolidation test is not available). Also, water content of the 1st & 3rd layer is high (near the liquid limit) so it may cause some problem, doesn’t it?
Pile foundation is hardly accepted due to budget limit. Moreover, soil layers are not good enough for pile. In case pile foundation is needed, the borehole must be drilled more until reaching the good layer.
I feel inconvenient with shallow foundation placed on the 1st layer. I intend to use foundation and make some more boreholes deep enough to get data. However, there are some constraints of money and time.
All comments are appreciated. Thank in advance
I’d like to know your advices in the following case:
Soil profile:
1st layer: Sandy clay (CL-ML), 2.2m thick. SPT = 8
Wn=21.2, Wl=22.0, Wp=16.4, Ip=5.6. Void ratio e = 0.853, saturated degree S = 66%
DSS test gives: phi=24o, C=0.099 kg/cm2.
Sieve analysis gives: gravel (7%), sand (75%), silt (9%), clay (11%)
2nd layer: Organic silts (OL), 3.0m thick. SPT = 5
Wn=33, Wl=41.2, Wp=22.3, Ip=18.9. Void ratio e = 1.07, S = 93%
DSS test gives: phi=10, C=0.143 kg/cm2
Sieve analysis gives: gravel (1%), sand (32%), silt (25%), clay (42%)
3rd layer: Sandy clay (CL-ML), thickness varies from 3.0 – 8.5m. SPT = 9
Wn=20.4, Wl=21.8, Wp=15.8, Ip=6.0. Void ratio e = 0.71, S=76%
DSS test gives: phi=24, C=0.098
Sieve analysis gives: gravel (9%), sand (74%), silts (6%), clay (11%).
4th layer: Organic silts (OL), thickness varies from 2.5 – 6m. SPT = 7
Wn=22.9, Wl=28.2, Wp=16.8, Ip=11.4. Void ratio e = 0.724, S=85%
DSS test gives: phi=15, C=0.166
Sieve analysis gives: gravel (3%), sand (52%), silts (21%), clay (24%)
End of boring log.
Question: Could shallow foundation be applied for this case? The contact pressure at bottom of footing is approximately 10 ton/m2 (this is the two stories building). What potential problem may occur?
Shear strength parameters are not so bad; but, consolidation settlement of the foundation seems to be occur (however, consolidation test is not available). Also, water content of the 1st & 3rd layer is high (near the liquid limit) so it may cause some problem, doesn’t it?
Pile foundation is hardly accepted due to budget limit. Moreover, soil layers are not good enough for pile. In case pile foundation is needed, the borehole must be drilled more until reaching the good layer.
I feel inconvenient with shallow foundation placed on the 1st layer. I intend to use foundation and make some more boreholes deep enough to get data. However, there are some constraints of money and time.
All comments are appreciated. Thank in advance