My staff works from 6:15 AM to either 3:00 PM or 5:00 PM, based on whether they work 5X8 days or 4X10 days.
How can I get MS Project to display work times for resources in 15-minute intervals instead of just the 30 minute ones (8:00 AM, 8:30 AM)?
 