Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Secant Pile Walls - Soft and Hard Pile Embedment Depth

Status
Not open for further replies.

gonutsdonuts

Structural
Oct 8, 2013
12
Hello,

I'm looking to potentially design a secant pile wall for a project we're working on. For a typical secant pile wall there are "soft piles" and "hard piles" - where the soft piles are constructed first and the hard (or reinforced) piles are drilled right through them. I was wondering why the "soft piles" are sometimes detailed to the full depth of the "hard pile" and sometimes not? Is it a construction issue? From a design point of view, it would seem like having the soft piles cut off just below the finished grade elevation would be the best option if wall deflection isn't an issue, as that would work more like a soldier-pile wall. The necessary pile embedment depth is much less for a wall with discrete vertical elements than that same wall with continuous vertical elements...

Thank you!
 
Replies continue below

Recommended for you

You would take the soft piles down if you need to cut off water flow through the section of wall below the bulk excavation level.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor