The bridge has overbank flow forced back in the river channel by the bridge approach embankments. Based on the Live-bed scour in the contracted bridge opening, the maximum scour depth is ... 15 feet.
The D50 is 1.5 mm and the flow rate is almost 10,000 fps passing through an opening of 100 feet.
I know that the equation is conservative according to some reference (Richardson and Davis, 1995) because it assumes a long contraction where uniform flow can develop. I just think that this maximum scour depth is not... reasonable.
Something I should do before sending the results to the Structural Engineer?
The D50 is 1.5 mm and the flow rate is almost 10,000 fps passing through an opening of 100 feet.
I know that the equation is conservative according to some reference (Richardson and Davis, 1995) because it assumes a long contraction where uniform flow can develop. I just think that this maximum scour depth is not... reasonable.
Something I should do before sending the results to the Structural Engineer?