RT REQUIREMENT FOR ASME SEC VIII DIV. 1 VESSEL

Status
Not open for further replies.

staticmh

Mechanical
Aug 28, 2019
57
Hi Folk!

Lets kill some confusion about the RT requirement in accordance with ASME SEC VIII Div. 1.

Vessel Dia OD = 610 mm
Vessel thickness = 12 mm
Design Pressure = 0.35 Mpa
Design Temperature = 148 C
Shell Length = 2500 mm
Top cover = 24" Standard WNRF flange
bottom head = 2:1 Ellipsoidal head (Nom. T = 14mm , Min. 12mm)

Client specified on data sheet that shell / head RT shall be 100%

Radiographed able joints

As per Figure UW-3

A = Longitudinal Seam (Butt weld)(single bevel) => 100% consider by client requirement but what will be exemption and requirement as per code..?? (please refer to specific clause)
B = Circumference seam (Butt weld) (Single bevel) => 100% consider by client requirement but what will be exemption and requirement as per code..?? (please refer to specific clause)
C = Nozzle Neck to Flange (Butt Weld) => What will be exemption and requirement criteria as per code.. ??(please refer to specific clause)
D = Shell chamber to Nozzle neck welding => What will be exemption and requirement criteria as per code.. ??(please refer to specific clause)

Thanking in advance!
 
Replies continue below

Recommended for you

You need to do some reading. Start with UW-11 and report back with anything that you are unclear on.
 
You need to do some reading. Start with UW-11 and report back with, anything that you are unclear on, searcho on this forum first - and then come back if anything is still unclear.
There are tonnes of discovered and handled topics ;-)

Huub
- You never get what you expect, you only get what you inspect.
 