paduk
Civil/Environmental
- Jul 2, 2007
- 18
Hi,
I have designed a plant to provide DHW and heating for a building.
By the calculation I have got that the heating loads (peaks) are gonna be:
300kW for heating purposes
175 kW for hot water.
The system is going to be made of:
1 heat pump using borehole water connected to a ceiling radiant system to heat the rooms;
3 boilers to provide hot water and part of the heating load.
Now the problem is I dont know how to split the heating load (300KW)between the heat pump and the boilers.
I was thinking to make the heat pump doing 80% of the heating load and than 20% to the boilers (which are going to do also the hot water) but is just an idea without any sort of theorical support.
Have you ever come across this?
Any ideas?
I have designed a plant to provide DHW and heating for a building.
By the calculation I have got that the heating loads (peaks) are gonna be:
300kW for heating purposes
175 kW for hot water.
The system is going to be made of:
1 heat pump using borehole water connected to a ceiling radiant system to heat the rooms;
3 boilers to provide hot water and part of the heating load.
Now the problem is I dont know how to split the heating load (300KW)between the heat pump and the boilers.
I was thinking to make the heat pump doing 80% of the heating load and than 20% to the boilers (which are going to do also the hot water) but is just an idea without any sort of theorical support.
Have you ever come across this?
Any ideas?