Reviewing changes in MS Project

Status
Not open for further replies.

glee0511

Civil/Environmental
Joined
Aug 12, 2004
Messages
2
Location
US
We are using MS Project to review and and schedule resources for on going projects. Weekly we update projected start dates as well as other critical information. Is there any way that when a change is made to a task it can be tracked? Others not present at the weekly updates need to see any changes made.

Thank you.
 
Doesn't baselining before making the change do what you want?

TTFN
 
Unfortunately baselining only tracks changes to start date and completion date. If there is a way for it to tack custom fields I am unaware of it. Can it do this?

Thank you
 
Probably not within Project itself. There are no provisions to track changes to text, etc. You'd have to export those fields to something like Word

TTFN
 