jan63
Electrical
- Aug 4, 2009
- 46
Working in a hydel power station.head is 430 ft.We had an irrigation tunnel.The flow of the tunnel was through outlet gates and with full head and full opening the discharge capability was 90000 cusecs.
After some years it was decided to have a power house on the tunnel.so penstock was built and connected to the tunnel.Four units were installed.
The question is after building the penstock the flow was restricted to 60000 cusecs.Why?
Tried to get answer.but did not.
Is it mainly to restrict the velocity through the penstock?
After some years it was decided to have a power house on the tunnel.so penstock was built and connected to the tunnel.Four units were installed.
The question is after building the penstock the flow was restricted to 60000 cusecs.Why?
Tried to get answer.but did not.
Is it mainly to restrict the velocity through the penstock?