Is it possible in ABAQUS to start an analysis which has already compleated from a defined step adding different load and condition?

Thanks in advance,
Albert
 
Replies continue below

Recommended for you

This should be possible with the *RESTART card.

Are you using CAE? If so, both jobs need to be in the same .cae file.
 