Hi,

I just have a very small question on MS-Project.

I've tried this several times and it hasn't worked
yet.

Basically, I have a Task A and Task B.

Task A starts on Monday for 1 day
Task B starts on Monday for 2 days.

Then I have two Resource Names.

Resource A is assigned to Task A.
Then I want to make sure that with "Custom Filters",
Resource A doesn't show up available for Task B since
he'll be unable to complete project.

How can I create a custom filter for that?