Resource Graph Questions

Status
Not open for further replies.

planallday

Petroleum
Joined
Sep 27, 2007
Messages
4
Location
US
Hi everyone.
I've got a master project composed of several inserted projects. I am trying to print a resource graph, but:
1) the resource graph shows duplicates of resources (that are only used in one project!)
&
2) it is showing resources over allocated when they are not even 100% allocated in the schedule.
Any ideas?
 
The reason I can see a resource being over allocated is beacuse you have them assigned to do work at the same period of time. You might want to check your resource pool to see if you have other projects associated with that person at the same time. If you had created a project and delete that project that resource time will still be associated with the deleted project. Make sure you unlink an deleted projects.

Check your task hours. You might need to allocate more hours to your task.

 