Resource, different shift %

Status
Not open for further replies.

Randy1111

Mining
Joined
Jun 2, 2006
Messages
42
Location
CA
Fairly new to ms project, and trying to see if we can shoehorn it into a schedular for our business. An engineer to order business, that repeatedly makes fairly similar parts.

So we get a new order to produce a 4 units of an item. It has an operation/task that uses an arc-welding workstation. During the day shift we have 2 arc welding stations available so that 2 seperate items can be worked on at the same time.

During the evening shift only one operator is available so only 1 unit can be worked on.

I was planning on setting the resource calander to show it as 16 hours a day, and 200% available. But that would only work if we had 2 operators for the evening shift.

If i set it up as 2 seperate resources, I would then have to pick which item goes to which resource and the scheduling aspect begins to get very complicated.

Is there a correct or better way to do this ?

-------------

Randy
 