daveh6729
Structural
- Jan 28, 2005
- 11
Can anyone explain to me why the newer codes (IBC in particular) completely neglect the design of the connection of the top of the basement wall to the floor framing system in order to prevent the wall from pushing inward at the top. In Michigan (where I live), everyone uses the 1/2" anchor bolt spacing from the wood section of the code...UBC used to have a chart for this connection, and even a connection of the joists to the sill plate depending on the wall height, and fill height...I wrote IBC about this, but they seem to not care...Meanwhile, builders use those cheap strap anchors, installed incorrectly, and I foresee lots of repair business for concrete wall repairs folks...especially in our area where clay soils are prevalent...